The 69 kV, 12.5 km Culliton Creek Transmission Line was constructed north of Squamish for BluEarth Renewables through an EPC contract with Mountain Lake Construction. The transmission line engineering was awarded to CEC and included optimized routing, transmission line design in PLS-CADD, BC Hydro crossing designs, structure design/detailing, QA, and site support.
Categories: Transmission and Distribution Line, Consulting Engineering, Project Services