Each of these projects is a standalone 13 MW Organic Rankine Cycle (ORC) biomass plant fired by sawmill and forest residuals. At the time of construction, these plants were the largest implementation of the ORC technology utilizing waste biomass in the world. Both plants are fully operational and meet or exceed all performance targets. CEC provided a range of project and technical services throughout the project including project definition, preliminary engineering, utility interconnection, electrical and controls design, construction management, commissioning, and start-up support.
Categories: Biomass, Project Development, Consulting Engineering, Project Services